Enable Time-Phased Data Logging

Use this procedure to enable time-phased data logging and designate if baseline changes are significant or not, for the purpose of collecting data for the IPMR Format 3 report.

To enable time-phased data logging:

  1. Display the Project Audit Wizard.
  2. On the Log Operation page, do the following:
    • Select the Turn Log On option.
    • Select the Log time-phased changes option.
  3. Complete the pages of the Project Audit Wizard to enable time-phased data logging.
    Note: If the project log is already turned on prior to selecting the Log time-phased changes option you need to turn off the project log first.